Data processing center of the Bank, Zhytomyr
Field of operation: Data processing center for the Bank
The task is:
Implement a reliable emergency power supply scheme based on the FG WILSON diesel power plant in anti-vandal container design.
Diesel power plant model: P400E5
Maximum total electrical capacity: 1200 kVA
Task solution:
Turnkey implementation of the project was carried out on the basis of FG WILSON P400E5 diesel power plants, with a total electric power of 1200 kVA, an N + 1 redundancy scheme, with an external automatic refueling system and an underground fuel storage tank.